September-October: Site Preparation
October-November: Excavate & Pour Foundations
November 2016-January 2017: Erect Structural Steel
Photos — 2017
January-May: Framing Panels, Roofing, Windows
May: Building Shell Complete
May-October: Mechanical, Electrical, Plumbing
June-October: Interior Finishes
November: First Floor Finishes Complete
November-February: Furniture & Equipment Installation
2018
January: Second & Third Floor Finishes Complete